BESS Rohrsdorf

Client-side planning for a 407 MWh battery storage system.

Battery storage GermanyLichtBlick / Eneco
Aerial view of the BESS Rohrsdorf project site

The challenge

A full EPC contract with developer-managed interfaces (permits, grid connection) that must not become the critical path.

What we did

Reviewed the EPC contractor's programme for realism, integrated it into the project baseline, monitor progress and manage the developer interfaces.